Projects

Project 2016-01 - F ½ Road Mainline Upgrade

This Project upgrades a 3-inch line with a 6-inch waterline from 30 ½ Road to Allegheny.
Project No. Description Status Start Date End Date
2016-01 Project 2016-01 - F ½ Road Mainline Upgrade In Construction October 2016 December 2016

34 Road Main Line Upgrade

This Project upgrades a 4-inch water line to a 6-inch from E ¼ to F Road.
Project No. Description Status Start Date End Date
2016-02 34 Road Main Line Upgrade In Construction October 2016 December 2016

Highway 50 Crossing

This project replaces the 10-inch waterline installed in 1956 at 32 Road. The project is pending other agency approval and permitting.
Project No. Description Status Start Date End Date
2016-03 Highway 50 Crossing Bid Opening November 30 December 2016 Date March 2017

Destet Road and Highland Dr in Whitewater

This Project replaces 2-inch and 3-inch waterlines with 6-inch.
Project No. Description Status Start Date End Date
TBD Destet Road and Highland Dr in Whitewater In procurement December 2016 January 2017