BID ADVERTISMENT: None at this time.
Project 2022-05.2 Holland Street Line Upgrades -
Sorter Construction has completed the Holland Street Line Upgrade Project. Asphalt patches are scheduled to be completed. The District will advertise for final payment as required. Clifton Elementary now has a redundant water service connection and a new hydrant. The new water line connection will be utilized when the 10-inch line is replaced on F Road.
Project 2022-01 Coffman Road Transmission Line Project -
The engineering firm River City continues work on the re-design of the transmission line project. The design is nearly 100% complete.
Project 2022-03 Coffman Road Remote Fill Station -
A permit has been issued by Mesa County for the fill station. No new updates are available.
Project 2022-06 Highway 141 (32 Road) 10” Waterline Replacement/ Upgrade Project-
K & D Construction began work the week of March 6th. Construction began on D Road progressing toward D ¼ Road. Weather delays have affected this project.
CDOT F Road Project-
District staff continues to provide support as needed to CDOT. Water line work is not anticipated to begin until summer, however, the District has made minor water line changes to accommodate other construction activities.